MCQs Civil Engineering
1 Administrative head of public works department who is directly responsible to Governments is :
(a) Superientendent Engineer
(b) Chief Engineer
(c) Assistant Engineer
(d) Executive Engineer
Ans (b)
2 Milestone chart is an improvement over :
(a) Bar chart
(b) PERT
(c) CPM
(d) All of these
Ans (a)
3 A Gantt chart indicates
(a) Balance of work done
(b) Efficiency of project
(c) Comparison of actual process with scheduled
(d) Progress of project
Ans (c)
4 PERT stands for
(a) Program Estimation and Reporting Technique
(b) Process Estimation and Review Technique
(c) Program Evaluation and Review Technique
(d) Planning Estimation and Review Technique
Ans (c)
5 Stack time in PERT analysis
(a) can never be greater than zero
(b) is always zero for critical activities
(c) can never be less than zero
(d) is minimum for critical events
Ans (d)
6 The time by which a particular activity can be delayed without affecting the proceeding activities is known as
(a) total float
(b) free float
(c) interfering float
(d) independent float
Ans (d)
7 Slack time refers to
(a) an activity
(b) an event
(c) both event & activity
(d) None of the above
Ans (b)
8 The most popular type of organization used for Civil Engineering Construction, is
(a) Line organisation
(b) Line and staff organisation
(c) Functional organisation
(d) Effective organisatin
Ans (b)
9 The performance of a specific task in Network is known.
(a) Dummy
(b) Event
(c) Activity
(d) Contract
Ans (c)
10 A CPM network is to be drawn considering :
(a) Activity sequencing without resource availability
(b) Least total cost duration for activities
(c) Least toal cost duration for activities
(d) Activities sequencing considered resources availability for each individual activity separately
Ans (d)