MCQs ESE General Studies & Engineering Aptitude 

1. In the case of ionic bonding, the molecule is stable as long as the number of bonding electrons is
(a) Equal to the number of antibonding electrons
(b) Less than the number of antibonding electrons
(c) Greater than the number of anti-bonding electrons
(d) Equal to the number of antibonding neutrons
Ans. (b)
2. In a software project, COCOMO (Cost Constructive Model) is used to estimate
(a) Effort and duration based on the size of the software
(b) Size and duration based on the effort of the software
(c) Effort and cost based on the size of the software
(d) Size, effort and duration based on the cost of the software
Ans. (c)
3. How is the closeness or commonness of attitude, behaviour, trust and performance within the organization designated?
(a) Cohesion
(b) Morale
(c) Communication
(d) Leadership
Ans. (c)
4. Accessibility legislation is intended to
(a) Protect intellectual property
(b) Improve the usability of websites
(c) Make all websites easier to use for visually impaired people
(d) Improve access to services for disabled people in both the physical and the virtual worlds
Ans. (d)
5. PRAGATI is the acronym
(a) Pro-active governance and transparency in India
(b) Pro-active governance and timely implementation
(c) Primary governance for transparency in India (d) Promoting and accomplishing governance with assured and timely implementation
Ans. (b)
6. In a company assembly line, assembling gear boxes, five workers are assigned tasks who take 10, 8, 6, 9 and 10 minutes respectively. The balance delay for this assembly line is:
(a) 13.3%                     
(b) 14.0%
(c) 16.0%                     
(d) 43.3%
Ans. (b)
7. What is an optimizing strategy?
(a) Strategy of choosing the best possible solution considering all parameters
(b) Strategy of choosing a compromise solution (c) Strategy of choosing the least cost solution
(d) Strategy of choosing a solution on the basis of precedents
Ans. (a)
8. With reference to problem solving, fixation refers to
(a) Focused approach to problem solving
(b) Planned approach to problem solving
(c) Inability to see a problem from a fresh perspective
(d) Inability to comprehend the goals to be achieved
Ans. (c)
9. Concurrent engineering is implemented by involving a cross-functional team for design, production, testing and operational work
(a) During the project execution
(b) Long before the project execution
(c) Towards the end of the project execution
(d) After completion of the project execution
Ans. (b)
10. What is the full form of GPP?
(a) Green Public Policy
(b) Green Private Procurement
(c) Green Public Procurement
(d) Green Private Policy
Ans. (c)
For More MCQs ESE General Studies & Engineering Aptitude - Click Here