Question With Answer Civil Engineering
 

1  Administrative head of public works department who is directly responsible to Governments is :
(a)     Superientendent Engineer       
(b)     Chief Engineer
(c)     Assistant Engineer
(d)     Executive Engineer            
Ans   (b)
2   Milestone chart is an improvement over :
(a)    Bar chart   
(b)    PERT
(c)    CPM                             
(d)    All of these              
Ans  (a)
3   A Gantt chart indicates Gantt
(a)     Balance of work done             
(b)     Efficiency of project
(c)     Comparison of actual process with scheduled                       
(d)     Progress of project                   
Ans  (c)
4   PERT stands for PERT
(a)     Program Estimation and Reporting Technique             
(b)     Process Estimation and Review Technique
(c)     Program Evaluation and Review Technique                                    
(d)     Planning Estimation and Review Technique
Ans  (c)
5   Stack time in PERT analysis PERT
(a)     can never be greater than zero          
(b)     is always zero for critical activities
(c)     can never be less than zero                                  
(d)     is minimum for critical events       
Ans   (d)
6   The time by which a particular activity can be delayed without affecting the proceeding activities is known as
(a)     total float            
(b)     free float
(c)     interfering float                                
(d)     independent float                     
Ans  (d)
7   Slack time refers to
(a)     an activity  
(b)     an event
(c)     both event & activity                                 
(d)     None of the above                    
Ans   (b)
8   The most popular type of organization used for Civil Engineering Construction, is
(a)    Line organisation          
(b)     Line and staff organisation
(c)     Functional organisation                             
(d)     Effective organisatin                        
Ans   (b)
9   The performance of a specific task in Network is known.
(a)     Dummy               
(b)     Event
(c)     Activity                                  
(d)     Contract                 
Ans  (c)
10   A CPM network is to be drawn considering :
(a)    Activity sequencing without resource availability                  
(b)    Least total cost duration for activities
(c)   Least toal cost duration for activities                           
(d)    Activities sequencing considered resources availability for each individual activity separately
Ans  (d)
For More Question With Answer Civil Engineering - Click Here